Damages for Breach of Contract – Avoided or Reduced #64

Jan 01, 1985

CATEGORY:   
TAGS:               

PRINT


By Gerry Neely
B.A. LL.B.

Usually a judge will not assist a person who is in breach of contract, to avoid the consequences of that person's default. One would expect this to be particularly true where the contracting parties agreed that the default of one party would result in "pre-estimated" damages becoming payable to the other party. However, the interpretation of a statute or the application of a rule of law may help the defaulting party to avoid or to reduce the damages he agreed to pay.

In one case, a mortgagor signed a mortgage that provided that if default occurred, the mortgagee was not required to accept the principal sum unless "bonus of three months' interest was paid on the principal money in default". The mortgage was not paid at its date of maturity and the mortgagee refused to accept from the mortgagor the principal sum plus a per diem rate of interest at the mortgage rate, to the date of payment. Instead the mortgagee demanded an additional $30,000.00, an amount equivalent to three months' interest under the mortgage. Section 8 of the Interest Act of Canada prohibits a penalty on arrears of principal secured by a mortgage of real estate, that has the effect of increasing the charge on such arrears beyond the rate of interest payable on principal monies not in arrears. The mortgagee argued that the Section could not be applied in this circumstance because all of the principal monies were in default and therefore there was no principal money not in arrears. The British Columbia Court of Appeal rejected this argument and found that notwithstanding the agreement by the mortgagor to pay the bonus, the mortgagee could not collect it because that would be a breach of the Interest Act.1

In a second case, a developer paid a mortgage broker $30,750.00 and a life insurance company $61,500.00 as a fee for obtaining the mortgage loan and as a stand-by fee respectively. When the developer decided to sell rather than to build, it sued for the return of the stand-by fee. The agreement with the insurance company provided that the sum of $61,500.00 was to be retained by it as liquidated damages and not as a penalty, "it being agreed by all parties the $61,500.00 represents a fair estimate of such estimated damages". However, on the evidence presented by the insurance company, the Judge held that a generous allowance for costs of the insurance personnel involved in the approval of the loan, which were thrown away as a result of the developer's default, would be $15,000.00. The insurance company did try to prove that it had incurred a substantial loss of investment income as a result of setting aside the mortgage monies in short term investments which earned less interest than the long-term investments that would otherwise have been made. This evidence was too inconclusive to be accepted, but had it been, the additional investment loss would have established the pre-estimate of damages as being reasonable. However, the pre-estimate was "so extravagant, exorbitant or unconscionable" in relation to the actual loss suffered by the insurance company that it could only recover its actual loss.

During the course of cross-examinations, the developer discovered for the first time that the mortgage broker had also received a fee from the insurance company. The developer argued that the mortgage broker was its agent and that since the interests of the insurance company were adverse to those of the developer, the mortgage broker could not act for both without first obtaining the consent or waiver of the developer. The Judge agreed with the developer that the mortgage broker was in breach of its fiduciary duty to its principal, and ordered repayment to the developer of the sum of $30,750.00.

Therefore, in spite of the written contracts with both the mortgage broker and the life insurance company, the developer was reimbursed for substantially all of the money it had agreed to pay.2

  1. Adams Properties Ltd v. Sherwood Estates Ltd., 144, D.L.R. (3d), p. 562.
  2. Cumberland Realty Group v. B.L.T. Holdings Ltd., 32 R.P.R. 9..

To subscribe to receive BCREA publications such as this one, or to update your email address or current subscriptions, click here.

Without limiting the Terms of Use applicable to your use of BCREA's website and the information contained thereon, the information contained in BCREA’s Legally Speaking publications is prepared by external third-party contributors and provided for general informational purposes only. The information in BCREA’s Legally Speaking publications should not be considered legal advice, and BCREA does not intend for it to amount to advice on which you should rely. You should not, in any circumstances, rely on the legal information without first consulting with your lawyer about its accuracy and applicability. BCREA makes no representation about and has no responsibility to you or any other person for the accuracy, reliability or timeliness of the information supplied by any external third-party contributors.

What we do



Popular tags within Legally Speaking



Popular posts from BCREA

  • Housing Market Update – April 2024
    Apr 17, 2024
  • Mortgage Rate Forecast
    Mar 25, 2024
BCREA Public Website Preview
BCREA Public Website Preview
BCREA Public Website Preview
BCREA Public Website Preview